13 STAGES · 4 PHASES · 1 CRITICAL PATH
The question is always asked as a number of weeks, and answered honestly only as a sequence. A kitchen is not slow because trades are slow. It is slow because certain stages cannot begin until an earlier one is physically finished — stone cannot be templated off a drawing, and cabinetry cannot be manufactured off a maybe. Understand which links in that chain are fixed and you can read any program you are handed.
7 DECISIONS · BEFORE STAGE 06
04 PHASES
The thirteen stages group into four phases. Only one of them is loud. The phase that consumes the most calendar is the one where nothing appears to be happening at all.
LEAD-TIME DRIVEN
None of the three can be hurried by working longer days on site. Each has to be ordered, made and delivered before the stage that follows it can begin.
01 · CABINETRY
02 · STONE
03 · APPLIANCES
PARALLEL · SEQUENTIAL
Plenty runs at once. Cabinetry is being built while you finalise handles. Electrical rough-in and plumbing rough-in share the same open walls. Painting of adjacent rooms, flooring in a wider renovation and laundry joinery can all be sequenced into gaps rather than added to the end.
04 CAUSES · IN ORDER OF FREQUENCY
HOW TO READ A PROGRAM
Four questions. A builder who can answer them without hesitating has planned the job rather than priced it.
STAGE 01 · CONSULTATION